Projects

At OPS Group, we deliver civil, infrastructure, and utilities projects with a focus on quality, efficiency, and dependable results that stand the test of time. 

OPS Group civil services

Business Park, Hawera, South Taranaki

Client: South Taranaki District Council

Location: Hawera

Date: February 2024 - December 2025

Summary of Works: Our team delivered key civil and infrastructure works for the Hawera Business Park, including construction of new roads, installation of underground services, development of footpaths, and upgrades to two existing roads. The project supports ongoing growth and improved accessibility within the area.

 

 

OPS Group pipeline services

Universal Water Metering, New Plymouth

Client: New Plymouth District Council

Location: New Plymouth

Date: October 2022 - November 2025

Summary of Works: We were engaged to deliver water metering works across New Plymouth, including the installation of underground services and associated civil infrastructure. The project supports improved water management and long-term sustainability for the local network.

Universal Water Metering, Hamilton

Client: Hamilton City Council

Location: Hamilton City

Date: March 2026 - Present

Summary of Works: A major rollout of water metering infrastructure is set to take place across Hamilton, including the installation of underground services and associated civil works. The project will support improved water management and network efficiency for the growing region.

Tawhiti Road Rising Main Renewal, Hawera, South Taranaki

Client: South Taranaki District Council

Location: Hawera

Date: December 2025 - December 2025

Summary of Works: Renewed 750 m of DN150 sewer rising main using the advanced ASOE relining method, extending the life of critical wastewater infrastructure with minimal excavation and disruption. At the time of construction, this project achieved the longest ASOE relining installation completed in New Zealand, delivering a durable and cost-effective solution for South Taranaki District Council.

Taikatu and Auroa Water Main Renewal, Manaia, South Taranaki

Client: South Taranaki District Council

Location: Manaia

Date: January 2025 - March 2025

Summary of Works: Construction of approximately 8 km of DN180 PE water main as part of the Taikatu and Auroa Water Main Renewal project. The works improved the reliability and resilience of the local water supply network, helping to support continued service delivery to the surrounding communities.

Rata Street Sewer Main Renewal, Hawera, South Taranaki

Client: South Taranaki District Council

Location: Hawera

Date: February 2024 - June 2024

Summary of Works: Our team delivered a comprehensive wastewater pipeline renewal for South Taranaki District Council in Hāwera. The works included the installation of 500 m of DN300 gravity sewer and 1.2 km of DN225 rising main, enhancing the performance and resilience of the local wastewater network.